Back

Who we are

Anchored in Switzerland and internationally active, WALO is managed as a family business in the 4th and 5th generation. For over 100 years, WALO has focused on the combination of consistency and innovation.


Overview
Back

What we do

WALO is active as an innovative total solutions company in all markets of the construction industry. The family-owned company has established itself as a reliable partner in the construction industry and infrastructure projects in Switzerland and worldwide with its decades of experience and the permanent development of sustainable as well as economical solutions.


Overview
Back

Projects

We have successfully implemented many challenging projects. Therefore, we proudly let our references speak for our work.


Overview
Back

Products

Whether residential, industrial, healthcare, outdoor or for sports and leisure facilities - seamless floor coverings have to meet a wide variety of requirements on a permanent basis.


Overview
Back

Career

Good buildings and thus satisfied customers require precise construction work. All our employees, from unskilled workers to engineers, play a key role in ensuring that we achieve this goal time and time again.


Overview
2022 04 08_Goldach_Kesswil_SBB Zertifizierung_Thumbnail Social Media-3

Road renewal Kesswil

Due to the short construction period and the comprehensive logistics planning, the pavement renewal at the Kesswil train station presented the entire team with major challenges, all of which, however, were mastered excellently.

Tightly timed work steps

To meet the time challenge, the work steps had to be precisely interlocked. This required close coordination between the various service centers for transport and logistics, civil engineering, track construction and road construction. The coordination was handled by Raphael Reber, site manager for civil engineering.



Sophisticated logistics concept

In order to keep to the tight schedule, it was necessary to ensure that the trucks could deliver the material to the right place at the right time. At the same time, this was jeopardized by the increased traffic volume of around 1,000 trucks and the rail replacement buses. Raphael Reber therefore worked together with the municipality and the SBB to develop a logistics concept within a very short time, which on the one hand withstood the increased traffic volume and on the other hand ensured that the material reached the construction site on time.

A temporary bridge was used to further calm the traffic in the village of 1,000 inhabitants and to bring the trucks to the construction site by a shorter route. In addition, a 600 m long construction slope was built along the construction site. This made it possible to bring the material as well as the machines up to the track. Coordinating the many trucks on this narrow feeder road was another challenge.



Savings of around 65 t CO2

Once the construction slope had been built, work could begin on demolishing the track. First, the rails were removed and then the old ballast was excavated. This was transported directly to the Schuppis washing plant in Goldach, where it was washed and processed. Due to the washed material and the resulting shorter transport routes, WALO was able to guarantee the customer a saving of around 65 t of CO2.

Samples of the old ballast were sent directly to the WALO laboratory in Schlieren. There, the material was tested for grain gradation, sharpness and resistance using the Los Angeles test. The test results were immediately made available to SBB for testing.



High-quality foundation paving

Meanwhile, on the job site, the subgrade rehabilitation continued. For this purpose, the foundation including the drainage profile was excavated to a depth of 1.30 m and a new drainage system was installed. In order to ensure optimum foundation quality, Ivan Breitenmoser, road construction foreman, worked with various paving and compaction methods. The compaction was recorded in terms of area and could thus be handed over to the SBB for quality control.

At the beginning, the 50-centimeter-thick foundation layer was spread and compacted in a first step with the 3D-controlled Mecalac +-20mm and the feeder, so that a detailed rough grading +- 10mm could be achieved for the second layer.  With the help of the Bomag combination roller, which is upgraded for recording the dynamic surface compaction

Would you like to learn more about our construction site? In the video, our construction foremen tell you more about their work on the Kesswil project.

placeholder_hero_3

Contact us

We appreciate your interest in the WALO Group and will be happy to answer any questions you may have.

© 2024 Walo Bertschinger. All rights reserved.