Who we are
Anchored in Switzerland and internationally active, WALO is managed as a family business in the 4th and 5th generation. For over 100 years, WALO has focused on the combination of consistency and innovation.
What we do
WALO is active as an innovative total solutions company in all markets of the construction industry. The family-owned company has established itself as a reliable partner in the construction industry and infrastructure projects in Switzerland and worldwide with its decades of experience and the permanent development of sustainable as well as economical solutions.
Projects
We have successfully implemented many challenging projects. Therefore, we proudly let our references speak for our work.
Products
Whether residential, industrial, healthcare, outdoor or for sports and leisure facilities - seamless floor coverings have to meet a wide variety of requirements on a permanent basis.
Career
Good buildings and thus satisfied customers require precise construction work. All our employees, from unskilled workers to engineers, play a key role in ensuring that we achieve this goal time and time again.
Locations
With our locations in three countries, we are successfully active for you worldwide.
The joint venture WALO–TRBA (50:50, Switzerland/Belgium) took on responsibility for the complete renovation of runway 15/33: heavy demolition, 3D milling of the foundation layer, footings and concrete pouring, modifications to the visual guidance system and surface marking work. The construction project was managed by Artelia and Sogeti Ingenierie Airports. For the heavy demolition of the central section, the team worked closely with Eberhard and Reproad.
The project required seamless coordination with the airport, which was still actively operational: every machine movement, shift handover and material flow had to be coordinated with the airport operators.
“Working on airport infrastructure of this scale means operating in an environment where everything happens at maximum intensity. It requires precise coordination between the different trades, meticulously planned construction phases and strict requirements concerning operation, safety and quality.” Ivan Richon, project manager at WALO.
More than 38,000 m² of runway was demolished in under 29 hours, working in a two-shift pattern. For the centre section (over 33,000 m²), two 100-tonne hydraulic excavators with special shovel buckets were used, with assistance from more than 25 dumper trucks (A30–B50) and around 30 more hydraulic excavators (14–86 t) for the sections along the sides. The foundation layer was then 3D milled using two milling machines. Special noise barriers were installed to reduce the effects of noise on the surrounding villages.
Demolition: more than 40,500 m² in less than 29 hours in a two-shift pattern
Simultaneous use: up to 500 people on the construction site
Dumper trucks: more than 25 (A30–B50)
Hydraulic excavators: around 30, including 4 weighing 86–100 t
Side sections: 7,500 m², more than 3,600 m³ excavated
Slipform pavers worked in succession across a paving width of 12.10 m: double layer with automatic dowel insertion (31 cm), finisher layer with automatic surface flattening (7 cm), surface treatment with automatic sprayer equipment A reserve unit was kept on standby for all concrete-laying equipment. Two mixing plants installed directly on the construction site supplied up to 250 m³ of concrete per hour. The side sections (7,500 m²) were finished using 9-metre slipforms and a 12-metre screed on foundation layers that had been laid beforehand.
Total concrete volume: more than 16,500 m³
Centre section: 1,368 m × 24.20 m, 38–40 cm thick, in 5 days
Concrete production: up to 250 m³/h
Daily record: 3,685 m³ in a single day
Cement: around 6,300 t, approx. 210 delivery vehicles
Runway 15/33 was put back into operation on 16 May 2026 as planned. The WALO–TRBA team would like to thank EuroAirport Basel-Mulhouse-Freiburg for its trust and the construction management team of Artelia and Sogeti Ingenierie Airports for coordinating this ambitious project.
Tobias Markert, CEO EuroAirport Basel-Mulhouse: " A clear schedule and the highest quality standards were crucial for the renovation of the main runway. WALO and TRBA met both of these requirements and played a key role in ensuring that the work could be completed earlier than planned. "
Walo Bertschinger SA Romandie
Z.I. Le Marais 6
1312 Eclépens
Road Construction & Civil Engineering
15 April – 16 May 2026
EuroAirport Basel-Mulhouse-Freiburg
Artelia / Sogeti Ingenierie Airports
Joint venture partners:
WALO Bertschinger AG / TRBA (50:50)
Subcontractors:
Demolition: over 40,500 m² in < 29 h
Concrete: more than 16,500 m³
Daily record: 3,685 m³ concrete
Slipform pavers: 4 units used
Concrete production: up to 250 m³/h
Cement: approximately 6,300 t
Up to 500 people on site
We appreciate your interest in the WALO Group and are happy to answer any questions you may have.
Headquarters
Giessenstrasse 5
Postfach, 8953 Dietikon 1