Who we are
Anchored in Switzerland and internationally active, WALO is managed as a family business in the 4th and 5th generation. For over 100 years, WALO has focused on the combination of consistency and innovation.
What we do
WALO is active as an innovative total solutions company in all markets of the construction industry. The family-owned company has established itself as a reliable partner in the construction industry and infrastructure projects in Switzerland and worldwide with its decades of experience and the permanent development of sustainable as well as economical solutions.
Projects
We have successfully implemented many challenging projects. Therefore, we proudly let our references speak for our work.
Products
Whether residential, industrial, healthcare, outdoor or for sports and leisure facilities - seamless floor coverings have to meet a wide variety of requirements on a permanent basis.
Career
Good buildings and thus satisfied customers require precise construction work. All our employees, from unskilled workers to engineers, play a key role in ensuring that we achieve this goal time and time again.
Locations
With our locations in three countries, we are successfully active for you worldwide.
In the valley at Péry-La Heutte, the river, railway line, motorway and a cement works were all hemmed in together in a very confined space. In the midst of all this, WALO built two new bridges for the Swiss Federal Roads Office (FEDRO) over the N16 Transjurane highway – with traffic still running and barely any space for construction-related logistics.
Two new bridges made of cast-in-place concrete, each 150 metres in length, replaced an existing crossing over the N16 Transjurane highway at Péry-La Heutte, between Tavannes and Biel.
Construction period: July 2024 to December 2026.
Construction budget around CHF 40 million.
No more than three lorries per day for over 800 tonnes of falsework material.
Seven bridge panels with spans of up to 22 metres, without any intermediate supports.
Dismantling of the old bridge at night, in four parts, using a crawler crane with a load capacity of 750 tonnes.
Client: Federal Roads Office (FEDRO).
Background
At Péry-La Heutte, in the canton of Bern, there was practically no space for interim storage at the construction site: the river, railway line, motorway and cement works already occupied all of the narrow valley floor. Commissioned by FEDRO, WALO replaced an existing crossing with two new bridges between July 2024 and December 2026 – one for passenger vehicles, one for freight.
The TaBö combined planning association was responsible for coordinating the project. Given the lack of space, each load of material had to arrive at just the right time and in just the right place – not a moment sooner or later.
The first bridge was built during the first year of construction: 160 metres long, with a roundabout at each end and high supporting walls along the N16 highway. The second bridge, at around 140 metres long, followed in four stages – while the N16, the railway line and the cement works all remained open nearby.
The method
The formwork was not created on site, section by section, but emerged in digital form instead: a 3D model from the engineer was sent to the formwork supplier Doka, who prefabricated the individual elements on the basis of this. On site, it was then just a case of accepting these as just-in-time deliveries and laying them.
The falsework girders spanned a distance of up to 22 metres with no intermediate supports – a feat made possible thanks to girders resting on shoring towers, with 1000 kilonewtons bearing down on each support. Around 800 tonnes of steel were used for the falsework alone for the second bridge.
“No question about it, the formwork took us 20 to 30 per cent less time, compared with having to provide it on site in the conventional way”, explains Antonio D’Onofrio, the site manager from WALO.
Operational aspects
The old bridge was dismantled at night: the team cut the structure into two parts, lifted them up with a 750-tonne crawler crane, moved them away and only broke them up once they were on the ground. In total, the N16 highway and railway line had to close completely three times in order to provide the time windows required – including day, night and weekend work.
With no more than three lorries a day, every delivery had to fall right: any delay involving just one vehicle would have pushed the entire schedule back.
Team spirit
For Antonio D’Onofrio, the site manager at WALO, the biggest difficulty was not encountered at the construction site itself, but at the drawing board. In other words, coordinating falsework, formwork and time slots across a period of two years.
“The biggest challenge for me was the complex planning for the structure as a whole. Thanks to a strong team, and by incorporating a digital approach, we were able to deal with everything on time”, explains Antonio D’Onofrio, the site manager at WALO.
Context
Since the end of 2026, the region has benefited from having not one, but two separate bridges: one for passenger vehicles, one for freight, leaving traffic flowing more freely along a busy section of the N16 Transjurane highway.
The new bridge was opened on 18 September 2026. “This project shows how to coordinate a project at a challenging site, with road and rail traffic still running and without jeopardising safety or deadlines as a result”, explains Laurent Brugger, project manager at FEDRO.
The strength of any project is always partly reliant on the input of a strong team.
At Péry, our teams worked in very challenging conditions – with road and rail traffic still running, little space available, working at night and complex construction processes. What really counts in situations like this are dedication, flexibility and cooperation from all involved at the site. A big thank you to all the team for your dedication, day after day, and your contribution to this challenging project / Fabian Frieden, Head of Civil Engineering West
Sign up for our newsletter and receive regular updates on our latest products and services, upcoming events, as well as information on sustainability and compliance. You can unsubscribe at any time.
Walo Bertschinger AG
Headquarters
Giessenstrasse 5
Postfach, 8953 Dietikon 1